R584RESOLUTION NO. 584
A RESOLUTION OF THE CITY COUNCIL OF THE CITY OF
KENNEDALE, TEXAS, RECOMMENDING THE AWARD OF A BID FOR
THE 46TH YEAR COMMUNITY DEVELOPMENT BLOCK GRANT
PROJECT FOR WATERLINE IMPROVEMENTS IN THE 400 TO 600
BLOCKS OF THIRD STREET IN THE CITY OF KENNEDALE, TEXAS;
APPROVING FUNDING PARTICIPATION; AND PROVIDING AN
EFFECTIVE DATE.
WHEREAS, during the City Council meeting of April 211 20201 the City Council of
the City of Kennedale held a public hearing and approved the 46th Year Community
Development Block Grant (CDBG) Project to replace 1,374 linear feet of 12" asbestos -
cement waterline and 1,256 linear feet of 2" galvanized waterline with 12" PVC waterline
in the 400 to 600 blocks of Third Street, in the City of Kennedale, Texas; and
WHEREAS, the budget for the project approved on April 21, 2020, reflected an
estimated engineering and construction cost in the amount of $313,512.00, with the City
of Kennedale pledging funds in the amount of $133,512.00; and
WHEREAS, during detailed engineering, it was discovered that one lot at the end
of Third Street did not provide for the 50 feet of right-of-way necessary to complete the
project; and
WHEREAS,
in order to avoid extensive time delays, the
City has
chosen to realign
the waterline which
requires removing
and disposing asbestos
cement
pipe; and
WHEREAS, the City desires to accept the low bid from Excel 4 Construction in the
amount of $409,064 and approve City funding participation in the amount of $244,063.
NOW, THEREFORE, BE IT RESOLVED BY THE CITY COUNCIL OF THE CITY
OF KENNEDALE, TEXAS, THAT:
SECTION 1. That all matters stated in the preamble of this resolution are true and
correct and are incorporated herein as if copied in their entirety.
SECTION 2. That the City of Kennedale accepts the low bid from Excel 4
Construction in the amount of $409,064 and requests that Tarrant County award the
contract for the waterline improvements in the 400 to 600 blocks of Third Street to Excel
4 Construction.
SECTION 3. That the City of Kennedale pledges to fund $244,063.00 to Tarrant
County for the 46fh Year CDBG Project for the Third Street waterline rehabilitation project.
SECTION 4. That this Resolution shall be effective upon its passage.
PAGE
7 of 2
R5�•i CITY
OF
I<EMIJ�D/�I. F, 7X
2021
PASSED, ADOPTED, AND APPROVED BY THE CITY COUNCIL OF THE CITY
OF KENNEDALE, TEXAS, THIS THE 20TH DAY OF APRIL, 2021.
APPROVED:
rN
11
ATTEST:
7V (.��
CITY SECRETARY, LESLIE E. GALLO AY
PAGE 2 of 2
R SD4 CIT`! O� KENN EDAI_F, "fH 7_021