R74-01KENNEDALE RESOLUTION NO. 74 -1
Whereas, the City of Kennedale, Texas
Legal Name of Applicant
has made application to the Texas Water Quality Board and the
Environmental Protection Agency for a federal grant pursuant to
the Federal Water Pollution Control Act Amendments of 1972, Public
Law 92 -500, and the rules and regulations thereto
Now Therefore, Be It Resolved by the above named applicant
that the application for which federal grant assistance has been
requested pursuant to the Federal Water Pollution Control Act
Amendments of 1972, Public Law 92 -500, will be constructed to
completion in accordance with the laws, rules, and regulations and
with the following project schedule.
Project Schedule Item Date of Action
Infiltration /Inflow Analysis .
Initiated December 1973
Completed
Submitted to State (TWQB)
Preliminary Engineering Study
Initiated
Completed
Report Completed
Submitted to State (TWQB)
April 15, 1974
April 30, 1974
1972
1972
1972
197
Project Schedule Item
Date of Action
Infiltration /Inflow Evaluation Survey (if needed)
Initiated As of Jan. '74, Not Know
whether evaluation survey
Completed will be required. If required
69 n
Report Completed Say August '74
Submitted to State (TWQB)
Final Engineering /Feasibility Study
Initiated
Completed
Report Completed
Submitted to State (TWQB)
Environmental Assessment
Initiated
Completed
Public Ilear.ing Advertised
Public Hearing Conducted
Environmental Assessment
Finalized
Submitted to State (TWQB)
The Regional Planning Agency
Comments and Approvals Completed
Submitted to State (TWQB)
August '74
Except for possible revisions
that cou ld be necessitated
by I/I Analysis, the Final
Eng'r Rept. and Feasibility
Study is considered to ave
been complete in 1972.
1973
June 1973
M ay 21, 1973
June 25, 1973
J 1973
June 29, 1973
August 1972
May 1973
Final Plans and Specifications
Initiated
Completed
Submitted to State (TWQB)
1972
April 1, 1974
May 1974
_2_
Project Schedule Item
Advertise for Construction Bids
within the clays indicated after
authorization to advertise for
bids has been issued
Submit Bid Opening Documents
within the days indicated after
the bid opening date
Award Construction Contract
within the days indicated after
authorization to award the
contract has been issued
Initiation of construction
Within the days indicated after
the award of the contract
Complete Construction
within the days indicated after
initiation of construction
Availability of Financing runds
for applicants share of the
project costs
Availability of the Site(s)
for the project facilities
Date of Action
30
d
10 days
14 d-ws
45 days
150
da
Availa Now (Jan. 1974)
Most available by Jan. 1974
Complete by February 1974
Be it further resolved, that the above named applicant under-
stands that the above project schedule must be approved by the
Texas Water Quality Board and the Environmental Protection Agency,
and that once a project schedule has been approved, no changes
will be authorized without first receiving approval of the change
from the Texas Water Quality Board and the Environmental Protection
Agency. The applicant further understands that schedule modifications will
be approved where delays have been caused by either. E. P. A. or Texas Water
Quality Board.
-3-
Passed, approved and adopted this 10th day of January ,
19 7_
APPROVED:
Si da urZ an(T Title of Official
Governing Body - N. T. Childres, Mayor
of the City of Kennedale, Texas
(Seal)
ATTEST:
Signature and Title' Official
Authorized to Attest
Evelyn Templeton, City Secretary
-4-